Foundation Design for Slabs and Footings

Table of contents

Foundation design for slabs and footings is the process of determining the size, depth, and reinforcement configuration of building foundations to safely transfer structural loads to the ground. In Australia, residential foundation design is governed by AS 2870-2011, while commercial and industrial foundations follow AS 2159 (piling) and AS 3600 (concrete structures).

Types of Foundations

Shallow Foundations

Type Description Typical Use
Strip footing Continuous footing under load-bearing walls Residential, light commercial
Pad footing Isolated footing for columns Columns, posts, pillars
Stiffened raft slab Concrete slab with integral perimeter and internal beams Standard residential (more stable)
Waffle raft slab Grid of ribs (beams) with void formers between them Residential (moderately reactive sites)
Combined footing Multiple columns on one footing Close-spaced columns
Shoe / edge beam footing Edge beam thickening on a slab Low-reactive sites

Deep Foundations

Type Description Typical Use
Driven piles Precast concrete or steel piles driven to bearing stratum All soil types, high loads
Bored piles (CFA) Continuous flight auger piles cast in place Variable soil conditions
Screw piles Steel helical piles screwed into ground Reactive soils, limited access
Pier and beam Concrete piers at depth with suspended floor beams Highly reactive sites, sloping sites
Micro-piles Small-diameter drilled and grouted piles Restricted access, underpinning

Foundation Design Process

Step 1: Geotechnical Investigation

A site classification or geotechnical report provides:

  • Soil profile and classification
  • Bearing capacity
  • Reactivity (shrink/swell index)
  • Groundwater conditions
  • Slope stability assessment (if required)

Step 2: Determine Site Class (AS 2870)

The site class determines the foundation type and design parameters:

Site Class Typical Foundation Depth of Beam
A (sand/rock) Slab on ground, edge beam 300 mm
S (slightly reactive) Waffle raft or stiffened raft 450 mm
M (moderately reactive) Stiffened raft 600 mm
H1 (highly reactive) Stiffened raft 750 mm
H2 (highly reactive) Stiffened raft or pier and beam 900 mm
E (extremely reactive) Pier and beam Piers to > 2 m
P (problem site) Engineered solution Site-specific

Step 3: Structural Design

The structural engineer calculates:

  • Bearing pressure — load divided by footing area, must be ≤ allowable bearing capacity
  • Settlement — total and differential settlement within acceptable limits
  • Punching shear — resistance of slab/beam around column or wall
  • Bending moment — reinforcement required in beams and slab
  • Crack control — reinforcement to limit cracking from ground movement
  • Reactive soil effects — design for soil heave/shrinkage

Step 4: Foundation Detailing

Detail Purpose
Concrete strength (f'c) 20–32 MPa typical for residential; higher for aggressive soils
Cover to reinforcement 20–50 mm depending on exposure class
Waterproofing For below-ground walls and slabs
Articulation joints For long walls to control cracking
Damp-proof membrane Under slab on ground floors

Bearing Capacity

Allowable Bearing Capacity (Typical Values)

Material Allowable Bearing Capacity (kPa)
Hard rock > 1,000
Soft rock 500–1,000
Very dense sand / gravel 300–500
Dense sand 200–300
Stiff clay 150–250
Firm clay 75–150
Loose sand 50–100
Soft clay < 50

Bearing Capacity from SPT N-Values

For sands: q_all (kPa) ≈ N × 20 (Terzaghi rule of thumb)

For clays: q_all (kPa) ≈ N × 6.25 × 1/FoS

Settlement Considerations

Foundation Type Maximum Total Settlement Maximum Differential Settlement
Residential slab (AS 2870) 30–40 mm 20 mm
Commercial footing 25 mm 15 mm
Mat foundation 50 mm 25 mm
Piled foundation 10–25 mm 5–10 mm

Ground Improvement for Foundations

When in-situ soils are inadequate, ground improvement may be required:

Issue Improvement Method
Low bearing capacity Remove and replace, stone columns, deep soil mixing
Reactive clay Lime stabilisation, controlled filling
Loose sand / liquefaction Vibro-compaction, stone columns, compaction grouting
Soft clay / high settlement Preloading + PVD, deep soil mixing
Filled ground Dynamic compaction, preloading, piles through fill

Australian Standards

Standard Title
AS 2870-2011 Residential Slabs and Footings
AS 2159-2009 Piling — Design and Installation
AS 3600-2018 Concrete Structures
AS 1726-2017 Geotechnical Site Investigations
NCC (National Construction Code) Building Code Requirements

Frequently Asked Questions

What is the difference between a stiffened raft and a waffle raft?

A stiffened raft has beams that are formed by excavating trenches in the ground. A waffle raft uses polystyrene void formers on a flat ground surface with concrete ribs cast between them. Waffle rafts are typically used on moderately reactive sites where excavation is more difficult.

Do I always need a geotechnical investigation?

Yes. The NCC requires a site-specific classification for all new residential construction. Without it, no structural engineer can certify the foundation design.

Can a geotechnical investigation identify groundwater problems?

Yes — groundwater depth, flow characteristics, and potential construction implications are part of a standard geotechnical investigation.

What happens if unexpected soil conditions are found during excavation?

If the conditions exposed in the excavation differ from the geotechnical report assumptions, a geotechnical engineer should inspect the excavation and may recommend foundation modifications.