Pile Capacity (Static Analysis and Testing)

Table of contents

Pile capacity is the maximum load that a pile foundation can safely support without failure.

Pile capacity is a fundamental concept in deep foundation design, used when surface soils are too weak to support structures using shallow foundations.

Piles are used when:

  • Surface soils are too weak for shallow foundations
  • Settlement must be limited
  • Lateral loads are large (bridges, marine structures)
  • Uplift forces exist (basements, wind)
  • Soil conditions are variable or unpredictable

Pile Types

Pile Type Typical Diameter Maximum Load Common Use
Driven precast concrete 250–600 mm 1,000–5,000 kN General buildings, bridges
Driven steel H-piles 200–400 mm 500–3,000 kN Structures needing high capacity in dense soils
Driven steel pipe piles 300–2,000 mm 2,000–20,000 kN Marine, bridges, major infrastructure
Bored piles (CFA) 300–1,200 mm 1,000–8,000 kN Urban sites, noise-sensitive areas
Bored piles (under-reamed) 600–3,000 mm 5,000–30,000 kN High-capacity single piles
Screw piles 100–600 mm 100–1,500 kN Light structures, residential
Micropiles 100–300 mm 300–2,000 kN Restricted access, underpinning

Load Transfer Mechanism

Load (Q)
   │
   ▼
┌──────────────────┐
│  Pile shaft      │◄── Skin friction (Qs) — distributed along shaft
│                  │
│                  │
│                  │
│  Pile toe        │◄── End bearing (Qb) — concentrated at base
└──────────────────┘

Total capacity: Qu = Qs + Qb = ∑(friction × area) + (bearing × area)

Static Analysis (Ultimate Pile Capacity)

General Equation

$$ Q_u = Q_s + Q_b - W $$

Where:

  • $Q_s$ = shaft resistance (skin friction)
  • $Q_b$ = base resistance (end bearing)
  • $W$ = self-weight of pile (often neglected for compression piles)

Shaft Friction in Cohesive Soils ($\alpha$ Method)

$$ Q_s = \sum \alpha \cdot s_u \cdot A_s $$

Where:

  • $\alpha$ = adhesion factor (0.3–1.0, depending on $s_u$)
  • $s_u$ = undrained shear strength
  • $A_s = \pi D L$ = shaft surface area

$\alpha$ values (Terzaghi-Peck API method):

$s_u$ (kPa) $\alpha$
< 25 1.0
25–50 1.0–0.8
50–100 0.8–0.6
100–150 0.6–0.4
150–200 0.4–0.3
> 200 0.3–0.25

Alternative — $\beta$ Method (effective stress):

$$ Q_s = \sum \beta \cdot \sigma'_{v0} \cdot A_s $$

Where $\beta = K \tan \delta$ (typically 0.2–0.6 for clays).

Shaft Friction in Cohesionless Soils ($\beta$ or $K$ Method)

$$ Q_s = \sum K \cdot \sigma'_{v0} \cdot \tan\delta \cdot A_s $$

Where:

  • $K$ = coefficient of lateral earth pressure on shaft
  • $\delta$ = soil-pile interface friction angle ($\delta \approx 0.5\phi'$ to $0.8\phi'$)
  • $\sigma'_{v0}$ = effective vertical stress
Soil Type $K$ (driven piles) $K$ (bored piles)
Loose sand 1.0–1.5 0.5–0.7
Medium dense sand 1.0–2.0 0.7–1.0
Dense sand 1.5–3.0 0.7–1.2

Interface friction angle:

Pile Material $\delta$
Smooth steel 20°–25°
Rough steel 25°–30°
Concrete 0.75$\phi'$–1.0$\phi'$
Timber 0.75$\phi'$–1.0$\phi'$

End Bearing

In cohesive soils:

$$ Q_b = N_c \cdot s_u \cdot A_b $$

Where $N_c$ = bearing capacity factor (typically 9 for deep foundations).

In cohesionless soils (Terzaghi's method):

$$ Q_b = (\sigma'_{v0} N_q + 0.5\gamma DN_\gamma) \cdot A_b $$

For deep foundations, $N_q$ is much larger than for shallow footings. A common approach:

$$ q_b = N_q^* \cdot \sigma'_{v0} $$

Where $N_q^*$ is obtained from Meyerhof's deep foundation charts.

$\phi$' (°) $N_q^*$ (driven piles) $N_q^*$ (bored piles)
26 10 5
30 25 12
34 60 30
38 150 80
40 250 140
42 400 250

Limiting end bearing values (Meyerhof):

Soil Type $q_{b(limit)}$ (MPa)
Loose sand 5
Medium sand 10
Dense sand 15–20
Very dense sand 20–30

Pile Capacity from In-Situ Tests

SPT Method (Meyerhof)

Driven piles — end bearing:

$$ q_b = 40N \frac{D}{B} \leq 400N \quad \text{(kPa)} $$

Where $D$ = embedment depth, $B$ = pile width, $N$ = average SPT N-value at toe (typically over 8B above to 4B below).

Driven piles — shaft friction:

$$ q_s = 2N \quad \text{(kPa)} \quad \text{(for displacement piles)} $$ $$ q_s = N \quad \text{(kPa)} \quad \text{(for non-displacement piles)} $$

CPT Method

End bearing:

$$ q_b = \frac{q_{c(avg)}}{F} $$

Where $F$ = factor (typically 1.5–3.0 for driven piles, 1.5–6.0 for bored piles).

Shaft friction (Nottingham & Schmertmann):

$$ q_s = \alpha_s \cdot f_s $$

Where $f_s$ = CPT sleeve friction and $\alpha_s$ = 0.5–1.0 depending on pile type.

De Ruiter & Beringen (OCR-based):

For piles in clay: $q_s = \alpha \times q_c$

Soil Type $\alpha$
Normally consolidated clay 0.03–0.05
Overconsolidated clay 0.02–0.04

Pile Groups

Efficiency

$$ \eta = \frac{Q_{u(group)}}{n \times Q_{u(single)}} $$

Where $n$ = number of piles.

Converse-Labarre formula:

$$ \eta = 1 - \frac{\theta}{90°} \cdot \frac{(n' - 1)m + (m - 1)n'}{mn'} $$

Where $m$ = number of rows, $n'$ = number of piles per row, $\theta = \tan^{-1}(D/s)$.

Typical group efficiency:

Spacing Group Efficiency
2.5D 0.6–0.7
3D 0.7–0.8
4D 0.85–0.95
6D+ 1.0

Group Settlement

For pile groups in clay, the equivalent raft method is commonly used:

  • An equivalent footing is placed at depth $2/3L$ from the pile tip
  • Settlement of this equivalent raft is calculated using 2:1 load spread

Negative Skin Friction

When fill or soft soil settles around a pile:

  • Downdrag force develops on the shaft
  • Neutral plane is where soil settlement = pile settlement
  • Above neutral plane: negative (downward) friction acts
  • Below neutral plane: positive (upward) friction acts
$$ Q_{neg} = \int_{0}^{z_n} \beta \cdot \sigma'_v \cdot \pi D \, dz $$

Pile Load Testing

Static Load Test (Maintained Load)

Procedure (AS 2159):

  1. Load is applied in increments (typically 20–25% of design load)
  2. Each increment held until settlement stabilises
  3. Maximum test load = 150% of ultimate design load (or to failure)
  4. Unload in stages, recording rebound

Cyclic test:

  • Load-unload cycles to separate shaft and base resistance
  • Typically 3 cycles maximum before loading to failure

Interpretation of Static Load Test

Load (kN)
   ▲
   │         ┌─────── Failure load
   │        / 
   │       /      ──── Elastic line
   │      /
   │     /
   │    /
   │   / ──── Plastic failure
   │  /
   │ /
   └────────────────────► Settlement (mm)

Failure criteria (Davisson, 1972):

$$ \delta_f = \frac{Q L}{A E} + \frac{D}{120} + 4 \quad \text{(mm)} $$

Where $\delta_f$ is the settlement defining failure.

Brinch Hansen 80% criterion:
The load at which the settlement curve reaches a slope corresponding to 0.08 mm/kN (for piles < 600 mm diameter).

Dynamic Load Testing (PDA)

  • Instrumented hammer impact measures force and velocity
  • Pile Driving Analyzer (PDA) computes:
    • Static capacity (using CASE method or CAPWAP analysis)
    • Driving stresses (compression, tension)
    • Pile integrity
    • Hammer efficiency
Pile Type Accuracy Compared to Static Test
Driven piles ±15–25%
Bored piles ±20–35% (less reliable)

Rapid Load Test (Statnamic)

A controlled explosion/burn drives the pile:

  • Load duration: 100–200 ms (between static and dynamic)
  • Analysis uses unloading point method (UPM)

Advantages over static test:

  • Faster: 1–2 days vs 7–14 days
  • Higher capacity: can test up to 30 MN
  • Safer: no large reaction system

Bi-Directional Load Test (Osterberg Cell / O-Cell)

Hydraulic jacks embedded within the pile shaft push against a steel plate, loading the pile both upwards (shaft friction) and downwards (base resistance):

  • Measures shaft and base components separately
  • No reaction system needed
  • Up to 30 MN or more test capacity

Structural Design of Piles (AS 2159)

Design Approach

AS 2159 uses a limit state design approach:

$$ R_d \geq S^* $$

Where $R_d$ = design geotechnical strength, $S^*$ = design load effect.

Geotechnical Strength Reduction Factors ($\phi_g$):

Pile Type Method of Capacity Determination $\phi_g$
Driven piles Static analysis, verified by testing 0.65–0.85
Driven piles Static analysis only 0.40–0.65
Bored piles Static analysis, verified by testing 0.55–0.75
Bored piles Static analysis only 0.35–0.55
Any pile Static load test to failure 0.70–0.85
Any pile Dynamic testing (PDA + CAPWAP) 0.65–0.80

Factor of Safety Equivalence

$\phi_g$ Equivalent FS (approx.)
0.85 1.2
0.70 1.4
0.55 1.8
0.40 2.5

Lateral Load Capacity

Elastic Method (Reese & Matlock)

For piles with lateral load $H$ at ground surface:

$$ y_0 = \frac{H T^3}{EI} A_y + \frac{M_t T^2}{EI} B_y $$ $$ M_{max} = H T A_m + M_t B_m $$

Where $T = \sqrt[5]{EI/n_h}$ (characteristic length) and $n_h$ = modulus of subgrade reaction.

Typical $n_h$ values:

Soil Type $n_h$ (kN/m³)
Dry loose sand 2,000–5,000
Submerged loose sand 1,500–4,000
Medium dense sand 6,000–15,000
Dense sand 15,000–35,000
Soft clay 1,000–4,000
Stiff clay 5,000–15,000

p-y Curves (Nonlinear Method)

Defines lateral soil resistance ($p$) as a nonlinear function of pile deflection ($y$):

  • p-y curves are defined at depth intervals along the pile
  • The pile is analysed as a beam on nonlinear Winkler springs
  • More accurate than the elastic method for large deflections

Settlement of Single Piles

Elastic Settlement (Poulos & Davis Method)

$$ S = \frac{Q I}{E_s D} $$

Where $I$ = influence factor (depends on slenderness ratio $L/D$, stiffness ratio $K = E_p/E_s$, and soil Poisson's ratio).

Load Transfer Method (t-z Curves)

Defines shaft resistance ($t$) as a function of local displacement ($z$):

  • t-z curves are assigned along the shaft
  • End bearing q-z curve at the pile base
  • The pile is divided into elements and solved iteratively

Allowable Settlement

Structure Type Maximum Settlement
Single piles — bridge 25–50 mm
Pile groups — building 50–100 mm
Differential (between adjacent piles) 10–20 mm
Machinery foundations 10–25 mm

Defects and Integrity Testing

Test Method Detects Cost
PIT (Pile Integrity Test) Major defects, changes in cross-section Low
Cross-hole sonic logging Concrete quality, defects between tubes Moderate
Thermal integrity profiling Full shaft concrete quality Moderate
Core testing Concrete strength, actual length High
High-strain dynamic test (PDA) Capacity + integrity verification Moderate

Australian Standards

Standard Title Key Provisions
AS 2159 Piling — Design and Installation Geotechnical strength design, testing requirements
AS 2159-2009 (Amendment 1 2024) Updated test verification factors
AS 3600 Concrete Structures Concrete strength, cover, reinforcement
AS 4100 Steel Structures Steel pile design
AS 5100.3 Bridge Design — Foundations Bridge pile design
TfNSW QA R13 Piling NSW Roads specification

Example

Given: Steel H-pile 350×350 mm (HP 350) driven to 15 m in medium-dense sand ($\gamma = 18$ kN/m³, $\phi' = 34°$). $D_f = 15$ m, water table at 5 m.

Shaft friction:

$K = 1.5$, $\delta = 0.75 \times 34 = 25.5°$

Segment 1 (0–5 m, dry): $\sigma'_v$ at 2.5 m = 2.5 × 18 = 45 kPa

$q_{s1} = 1.5 \times 45 \times \tan(25.5°) = 32.2$ kPa $A_{s1} = 1.4 \times 5 = 7.0$ m² (perimeter ≈ 1.4 m) $Q_{s1} = 32.2 \times 7.0 = 225$ kN

Segment 2 (5–15 m, submerged): $\sigma'_v$ at 10 m = (5 × 18) + (5 × 9) = 135 kPa

$q_{s2} = 1.5 \times 135 \times \tan(25.5°) = 96.6$ kPa $A_{s2} = 1.4 \times 10 = 14.0$ m² $Q_{s2} = 96.6 \times 14.0 = 1,352$ kN

Total shaft: $Q_s = 225 + 1,352 = 1,577$ kN

End bearing:

$\sigma'_{v(toe)} = (5 \times 18) + (10 \times 9) = 180$ kPa $N_q = 40$ (for $\phi = 34°$, driven pile) $q_b = 180 \times 40 = 7,200$ kPa $A_b = 0.1225$ m² $Q_b = 7,200 \times 0.1225 = 882$ kN

Ultimate capacity: $Q_u = 1,577 + 882 = 2,459$ kN

Design capacity (with $\phi_g = 0.65$, no testing): $R_d = 0.65 \times 2,459 = 1,598$ kN