Temporary Works Design — Shoring and Excavation Support

Table of contents

Temporary works design covers the engineering of temporary structures needed to support excavations, retain ground, and provide safe working platforms during construction. Proper design of temporary works is essential for safety, constructability, and cost control.

What Are Temporary Works?

Temporary works are structures or systems required during construction but not forming part of the permanent works. In geotechnical engineering, common temporary works include:

  • Shoring systems — support for excavation walls
  • Temporary retaining walls — soldier piles, sheet piles, contiguous piles
  • Ground anchors and tiebacks — lateral support for shoring walls
  • Working platforms — stable surfaces for cranes and piling rigs
  • Temporary drainage — dewatering systems for excavation
  • Temporary slopes — cut slopes for access ramps or excavations

Excavation Support Systems

Soldier Pile and Lagging

Steel I-beams (soldier piles) are installed at regular spacing (typically 1.5–2.5 m) and timber or shotcrete lagging is placed between them as the excavation proceeds.

  • Suitable for: Stiff clays, weathered rock, sands (with dewatering)
  • Advantages: Cost-effective, flexible spacing, staged construction
  • Limitations: Not watertight, limited for very soft soils

Sheet Pile Walls

Interlocking steel profiles are driven into the ground to form a continuous wall.

Type Description Application
Straight web Low section modulus Light retaining, cut-off walls
U-section High bending resistance Deep excavations, waterfront
Z-section Very high bending resistance Deep excavations, heavy loads
  • Advantages: Watertight (if interlocked), reusable, quick installation
  • Limitations: Noise and vibration during driving, limited depth in dense ground

Contiguous Pile Walls

Reinforced concrete piles are installed at close spacing (typically 150–300 mm gaps) to form a retaining wall.

  • Suitable for: All soil types including rock
  • Advantages: High stiffness, can be installed in limited headroom
  • Limitations: Not watertight (gaps between piles), more expensive

Secant Pile Walls

Overlapping piles form a continuous, watertight wall. Alternate piles (primary piles) are installed first, then secondary piles cut into them.

  • Suitable for: Water-bearing soils, deep basements
  • Advantages: Watertight, high stiffness, can take vertical loads
  • Limitations: High cost, requires specialised equipment

Diaphragm Walls

Cast-in-situ concrete walls constructed in a trench under bentonite slurry.

  • Suitable for: Deep basements (20+ m), cut-and-cover tunnels
  • Advantages: Watertight, very high stiffness, part of permanent structure
  • Limitations: High cost, specialised contractor

Ground Anchors and Tiebacks

Ground anchors provide lateral restraint to shoring walls by transferring load to stable ground behind the excavation.

Types of Anchors

Type Description Typical Capacity
Temporary anchors Unbonded length, bonded length in grout 200–1,500 kN
Permanent anchors Double corrosion protection, grouted 300–3,000 kN
Macro-piles Small-diameter grouted pile used as anchor 100–500 kN

Anchor Testing

Test Purpose
Proof test Verify anchor capacity to 1.25–1.5× working load
Performance test Verify load-deflection behaviour
Suitability test Confirm design assumptions on-site

Working Platform Design

Design Parameters

A safe working platform must support the maximum loads of construction plant:

Plant Type Working Load (kPa) Typical Platform Thickness
Small excavator (< 20t) 50–80 300–400 mm
Medium excavator (20–40t) 80–150 400–600 mm
Piling rig 200–400 500–1,000 mm
Crawler crane (50–100t) 150–300 500–900 mm
Mobile crane outriggers 300–600 600–1,200 mm

Working Platform Design Process

  1. Subgrade investigation (CBR, DCP, plate load test)
  2. Platform thickness design (limit equilibrium or bearing capacity)
  3. Material specification (DGB-20, crushed rock, recycled aggregate)
  4. Construction quality control (lift thickness, compaction tests)
  5. Certification (safe working platform certificate)

Dewatering

Types

Method Suitable For Application
Sump pumping Small excavations, granular soils Simple, low cost
Wellpoints Shallow excavations, sands Close spacing, continuous pumping
Deep wells Deep excavations, variable soils Large volumes
Eductor wells Fine sands, silts Vacuum-assisted dewatering

Design Considerations

  • Predicted groundwater inflow
  • Drawdown radius of influence
  • Impact on adjacent structures (settlement from consolidation)
  • Water treatment and discharge (EPA requirements, trade waste)
  • Duration of operation

Key Design Checks

Check Requirement
Wall stability Overturning, sliding, bearing capacity
Structural capacity Bending, shear in wall elements
Anchor design Pullout capacity, corrosion protection
Global stability Deep-seated failure surface through anchor zone
Settlement behind wall Ground loss, consolidation from dewatering
Basal heave Bottom heave in soft clays
Groundwater control Inflow rates, filter design, settlement risk

Australian Standards and References

Standard Title
AS 4678-2002 Earth Retaining Structures
AS 4100 Steel structures (soldier piles, walers)
AS 3600 Concrete structures (piles, walls)
AS 1726-2017 Geotechnical site investigations
Safe Work Australia Excavation and shoring guidance
CIRIA C517 Temporary works design guidance
BS 8004 Foundations (retaining wall design)