Construction quality assurance (QA) verifies that work is carried out in accordance with the design, specification, and applicable standards: and that this is documented and auditable.
The core tool for structuring QA on Australian projects is the Inspection and Test Plan (ITP).
QA, QC and Concrete Testing
Quality assurance (QA) establishes the planned process, responsibilities and records. Quality control (QC) checks the material or work through inspections and measurements. A non-conformance is a departure from a stated requirement; it may concern the concrete, test procedure or missing evidence. An NCR is the record used to investigate and resolve that departure.
For concrete, separate the sampling record, laboratory result, supply-conformity assessment and construction release. A laboratory report is evidence: the person named in the contract or ITP decides whether the relevant hold point can be released. Conformity and structural adequacy are different questions, so an engineer’s assessment of a structure does not silently erase a supply non-conformance.
See the concrete testing overview, cylinder result guide and early-age stressing guide for the evidence needed at each stage.
Inspection and Test Plans (ITPs)
An ITP is a structured document listing every activity in a work process, the inspection or test required at each stage, the acceptance criteria, and who is responsible for sign-off.
| ITP Column | Content |
|---|---|
| Activity/Process Step | e.g. "Place reinforcement", "Pour concrete" |
| Reference Document | Drawing, specification clause, standard |
| Inspection/Test Method | Visual, survey, laboratory test |
| Acceptance Criteria | Tolerance, strength, compliance requirement |
| Responsibility | Contractor QA, superintendent, third-party |
| Records | Checklist, test certificate, photo, survey data |
Hold Points, Witness Points, and Review Points
| Point Type | Meaning |
|---|---|
| Hold Point (HP) | Work cannot proceed until the nominated authority issues the required release, normally documented in writing; the contract defines the evidence and whether attendance is required |
| Witness Point (WP) | Give the contractual notice and opportunity to attend; proceed only under the contract’s attendance, waiver and release rules after the notice period |
| Review Point (RP) | Documentation is reviewed, but does not halt physical work |
Hold points are typically placed before work becomes concealed or irreversible: e.g. before backfilling a trench, before concrete pour over reinforcement, before covering waterproofing.
Typical Hold Points by Trade
| Trade/Activity | Common Hold Point |
|---|---|
| Earthworks | Subgrade proof-rolling before pavement layers placed |
| Reinforced concrete | Reinforcement fixed, before pour |
| Piling | Pile integrity testing, before pile cap construction |
| Waterproofing | Membrane inspection, before covering/backfilling |
| Structural steel | Bolted/welded connection inspection before load-out |
Concrete ITP Example
This is a planning example; fill in the actual contract requirements before use.
| Activity | Record and decision basis | Release/responsibility |
|---|---|---|
| Pre-pour | Pour/element ID, approved drawings, reinforcement, formwork, services and nominated checks | Named pre-pour release authority |
| Sample and mould | Docket, mix, sampling frequency, method edition, specimen IDs, ages and curing plan | Laboratory/field technician under the approved ITP |
| Assess conformity | Adopted AS 1379 edition, sample grouping and project criteria | Nominated technical reviewer; NCR route for non-conformity |
| Stress, strip or de-prop | Specified strength/age, representative curing evidence, loading/sequence checks | Named construction-release authority, with written hold-point release |
Non-Conformance Reports (NCRs)
When work fails to meet acceptance criteria, it is documented via a Non-Conformance Report:
- Identify and document the non-conformance
- Assess extent (isolated defect vs systemic issue)
- Propose and approve a corrective action (rework, repair, or engineering acceptance of "as-is")
- Close out with verification that the corrective action was effective
Quality Management System Structure
Most Australian contractors operate QA under an ISO 9001-aligned quality management system:
Project Quality Plan
├── ITPs (per work activity)
├── Test Reports & Certificates
├── NCR Register
├── Design/Document Control
└── Audit Records
Relationship to Standards and Specifications
ITP acceptance criteria are drawn directly from:
- Project specification (often referencing AS standards, e.g. AS 3600, AS 1289 for geotechnical testing)
- Approved for Construction (AFC) drawings
- Manufacturer's requirements for proprietary products
Practical Notes
- Hold points only work if they're enforced: a hold point routinely bypassed under programme pressure defeats the entire QA system and creates liability exposure.
- NCRs should be closed with verified corrective action, not just a signature: recurring non-conformances usually indicate a process problem, not a one-off error.
- ITP acceptance criteria should be specific and measurable (e.g. "compaction ≥ 95% MDD") rather than vague ("adequately compacted") to be enforceable on site.