Formwork is the temporary mould that shapes concrete until it gains sufficient strength to support itself. In Australia, formwork design and construction is subject to the relevant AS 3610 parts, the adopted editions, project requirements and applicable WHS duties.
Formwork failures can involve inadequate pressure design, premature stripping, instability, deficient foundations, poor bracing or changes to the planned construction sequence.
Formwork Classification
Define the formwork system, design responsibility, consequence of failure and required independent checks in the project documentation. Do not assume a generic “Category 1/2/3” table establishes the AS 3610 requirements. Obtain the required design documentation, erection inspections and pour release, and control changes to the approved arrangement.
Design Loads on Formwork
Fresh Concrete Pressure
Fresh concrete can exert approximately hydrostatic lateral pressure while it behaves as a fluid:
Pressure = concrete density × gravitational acceleration × fluid head
With density in kg/m³, acceleration in m/s² and fluid head (height of fluid concrete above the point) in metres, pressure is in pascals (Pa). Divide by 1,000 for kilopascals (kPa). Illustrative calculation: 2,400 × 9.81 × 3 ÷ 1,000 ≈ 70.6 kPa at a 3 m head.
Rapid placement, delayed setting, some admixtures and highly flowable concrete can sustain high fluid pressure. Slower placement may permit lower pressure only where a validated design method and its conditions justify it. The designer must account for placement rate, temperature, mixture, setting, vibration, geometry and construction actions. The hydrostatic example is not a complete formwork design or permission to reduce pressure.
Other Loads
| Load Type | Description |
|---|---|
| Dead load | Self-weight of formwork and wet concrete |
| Live load | Workers, equipment, placement plant (e.g. concrete pump boom) |
| Wind load | On exposed vertical formwork (e.g. tall wall forms) |
| Impact load | Concrete discharge (pumping, chuting, skip) |
Falsework
Falsework supports formwork for elevated slabs and beams until the concrete gains strength. Key design considerations:
- Prop spacing and load path to ground or supporting structure
- Bracing against lateral instability (props are inherently unstable alone)
- Foundation bearing capacity beneath props (especially on suspended slabs below)
- Re-propping strategy if the slab below is not yet at full strength
Terms Used in Strength-Based Release
Striking or stripping means removing formwork. De-propping means removing load-carrying props. Re-propping and back-propping concern the planned support arrangement as construction progresses; use the definitions and sequence in the approved temporary-works design.
A construction load includes people, equipment, stockpiles and loads from floors above. Early-age strength is the concrete’s strength at the time of the proposed operation, which may be well before 28 days. A hold point prevents that operation until the nominated authority releases it against the required evidence.
A standard-cured cylinder shows specimen strength under standard conditions. It may not represent a cold, exposed slab or a heavily loaded lower floor. Agree the representative curing or approved maturity regime before the pour, make sufficient specimens, and tie each result to the correct element and operation. See compressive strength testing and early-age testing.
Strike Times
Release formwork and props against an approved strength and loading assessment, rather than a generic calendar-day table.
| Operation | Evidence required before release |
|---|---|
| Remove wall/column face forms | Adequate strength to avoid damage and instability; curing arrangements maintained |
| Remove slab/beam soffit forms | Approved removal sequence, strength evidence and remaining support arrangement |
| Remove or relocate props/back-props | Assessment of construction loads and all affected floors, strength and stability |
| Load a recently cast or PT floor | Designer’s required strength, stressing status, load limits and written hold-point release |
The nominated authority must approve the operation under the project’s formwork/temporary-works procedures. Tests intended to represent strength in the works need an approved representative curing or maturity regime.
Back-propping
Where a floor is loaded (by construction above) before reaching design strength, back-props transfer load down through multiple levels:
- Distributes load across several partially-cured floors rather than one
- Requires checking capacity of all floors in the back-propped stack, not just the immediate one
- Must be planned into the construction sequence, not improvised on site
Formwork Materials
| System | Application |
|---|---|
| Plywood/timber formwork | General purpose, complex shapes |
| Steel/aluminium modular systems | Repetitive elements (walls, columns) |
| Permanent formwork (e.g. steel decking) | Composite floor slabs |
| Climbing/jump formwork | Tall core walls, bridge piers |
Practical Notes
- Fresh concrete pressure calculations are highly sensitive to pour rate: a faster-than-planned pour (common with pump trucks) can exceed design pressure quickly.
- Check prop and falsework stability, bracing, foundations and load paths as well as member strength; isolated props need a designed stable system.
- Back-propping schemes must be checked as a system across multiple floors, not floor by floor in isolation.
Sources and Method Scope
This learning guide explains purpose, terminology and interpretation. It is not the full test method. Use the project-adopted standards, amendments, specification and controlled laboratory procedure for exact apparatus, timing, conditioning, calculations and decision rules.
- Workplace Health and Safety Queensland — construction codes of practice, including the Formwork Code of Practice.