When CMT labs do concrete tests, they need a system to record samples, do the tests, store the data, calculate and issue the reports. A LIMS helps with that.
This guide follows one example job from the laboratory's setup to the issued reports, and shows how concrete tests are recorded, calculated, checked and reported in a LIMS. The screenshots use GeotechOS Lab; the job, people and numbers are illustrative. Treat the workflow as an example of records to control, and verify each feature and calculation in the system your laboratory actually uses.
Terms
| Term | Meaning |
|---|---|
| LIMS | Laboratory information management system: software linking work requests, samples, specimens, equipment, results and reports. |
| Request, sample and specimen | A request is the booked work; a sample is the concrete collected from an identified delivery; a specimen is one cylinder, beam or prism made from it. |
| Traceability | The ability to follow a result back to its readings, equipment, specimen, curing record, source load and location. |
| Audit trail | A history of who changed a record, when, what changed and why. Corrections should remain distinguishable from the original entry. |
| Technical reviewer and signatory | People authorised under the laboratory’s system to check technical validity and authorise the report. The exact role arrangement depends on that system. |
| Provisional result | A result awaiting the required review or authorisation; it must not be mistaken for an issued report. |
| Microstrain | Length change divided by gauge length, multiplied by one million. 500 microstrain equals 0.05% strain. |
| Conformity assessment | Applying the specified acceptance rules to the relevant results. A software flag alone does not establish compliance or release construction work. |
The Example Job
The example is a road upgrade with two concrete pours, sampled on one site visit.
| Pour | Request | Concrete | Tests |
|---|---|---|---|
| Walls W1 to W4 | 1012 | 40 MPa self-compacting concrete with specified special properties | Slump flow and J-ring, air content, mass per unit volume, cylinders at 7 and 28 days |
| Pavement base | 1013 | 40 MPa pavement concrete with a flexural requirement, 50 mm slump | Slump, bleeding, flexural beams at 28 days, drying shrinkage prisms |
The same numbers are used all the way through, so you can follow a cylinder from the truck to the report.
The example includes properties additional to a simple strength grade. Confirm the correct supply-class designation and all additional properties with the supplier under the adopted AS 1379 edition; do not label a performance-specified SCC or pavement mix as normal-class solely because its strength is 40 MPa.
The tables show how to link records. They do not provide a complete sampling plan, method-validity check or supply-conformity assessment. Times, specimen counts and numerical limits must be configured from the adopted methods and contract. A screenshot may show only part of the record or an earlier example label; the full approved record governs.
The Steps
| Step | Purpose |
|---|---|
| Part 1: Set up the laboratory | The methods the laboratory runs, its equipment, and who may do each test |
| Part 2: Book the pour | A work request holding what the client has specified |
| Part 3: Sample the concrete on site | Each load's fresh tests and the specimens made from it |
| Part 4: Pick up and cure the specimens | Transport, demoulding and curing, with their times |
| Part 5: Break the cylinders and beams | Compressive and flexural strength |
| Part 6: Read the shrinkage prisms | Length readings over several weeks of drying |
| Part 7: Review and approve | An independent check before a result is reported |
| Part 8: Report and assess | The reports and the assessment against the specification |
What a LIMS Adds to a Concrete Test
- Linked identities. Each cylinder, beam and prism carries a label from the moment it is moulded, so its result stays tied to the load it came from.
- Times that are checked, not remembered. Demoulding, curing and test ages are worked out from recorded times, so a specimen handled late is noticed when it happens.
- Calculations held to the method. The software calculates and rounds each result the way the configured method says, from the unrounded figure, so every technician reports it the same way.
- Controlled review. Configure tester, reviewer and signatory permissions to implement the laboratory’s approved authorisation and impartiality arrangements.
- Reports that stay true to their data. An issued report is fixed; a correction is a new issue that says what changed.
None of this replaces the technician's judgement. A LIMS records what was done; it is still the tester who decides whether the concrete was sampled properly, whether a specimen was damaged and whether a result makes sense.
Part 1: Set Up the Laboratory
Before anything is recorded on site, three things are set up: the methods the laboratory runs, the equipment it runs them with, and the people allowed to do, check and approve each test. Accreditation to AS ISO/IEC 17025 asks for all three to be controlled, and a LIMS is where that control is visible.
Choose the Methods
A method in a LIMS is more than a name. It fixes which standard and edition apply, what is measured, how the result is calculated and how precisely it is reported. For the example job the laboratory runs the AS 1012 methods for slump, slump flow, air content, fresh density, bleeding, compressive strength, flexural strength and drying shrinkage.
Why it matters: the same measurements can give a different reported figure if the calculation or rounding is set up wrongly. When the method is configured once, centrally, every technician reports the same result from the same readings.
Register the Equipment
Every concrete test depends on equipment that must be in a known, checked condition: the slump cone and its base plate, the air meter, the density measure, the compression machine, the flexure frame, the length comparator and the drying room. The LIMS keeps a record of each item, its checks and calibrations, and stops a test being submitted with equipment that is overdue or locked out.
Some equipment also carries a value the calculation needs. In the example, the density measure's calibrated capacity (6.95 L) and the flexure frame's span (450 mm) are stored on their equipment records. The technician picks the measure or the frame rather than typing a figure from memory.
Authorise the People
Each person is authorised for the methods they are competent in, and for their role in them.
| Person | Role in the example |
|---|---|
| Sam (field technician) | Samples the concrete and makes the specimens |
| Alex (laboratory technician) | Cures, tests and reads the specimens |
| Jo (senior technician) | Technical review |
| Chris (approved signatory) | Approves results and issues reports |
Part 2: Book the Pour
A pour is usually booked before anyone goes to site. The booking records what the client has specified, so that the technician samples and tests the right things, and the report later says what the concrete was judged against.
| Detail | Walls (request 1012) | Pavement base (request 1013) |
|---|---|---|
| Specified properties | 40 MPa at 28 days plus SCC properties | 40 MPa at 28 days plus an illustrative 28-day flexural requirement of 4.5 MPa |
| Ordered slump or flow | Self-compacting | 50 mm |
| Loads | 4 | 2 |
| Fresh tests | Slump flow and J-ring, air, density | Slump, bleeding |
| Specimens per load | Cylinders at 7, 28 and 28 days | 2 beams at 28 days; 3 shrinkage prisms |
A pour may have several delivery loads. Apply the sampling plan: only a load actually sampled has a sample record, and a load can contain multiple production batches. The LIMS books the pour once as a request, and each load sampled on site becomes its next sample: S-1012A, S-1012B and so on, each with the booked tests.

The booking also schedules the site visit, so the pour appears on the field technician's phone on the day.

Part 3: Sample the Concrete on Site
Everything measured later depends on what happens at the truck. This part of the example follows two loads: S-1012A from the walls and S-1013A from the pavement. On site the technician records each load on a phone or tablet, and the LIMS works out each fresh result as the readings are entered.

Record the Load
A fresh concrete result means nothing without knowing which concrete it came from and how the sample was taken. The record holds the delivery docket, the truck, the mix, when and how the sample was taken, the temperatures, and any water added at site.
| Record | S-1012A (walls) | S-1013A (pavement) |
|---|---|---|
| Docket and truck | CD-88437, truck T31 | CD-88512, truck T07 |
| Load and poured so far | 6 m³ of 12 m³ | 5.5 m³ of 5.5 m³ |
| Sampled | 1:25 pm | 2:40 pm |
| Concrete / air temperature | 24 °C / 21 °C | 23 °C / 21 °C |
| Water added at site | None | None |

Workability
For the self-compacting walls concrete, the technician records the spread in two directions, the time to flow, the J-ring heights and whether the concrete blocked or segregated. The LIMS works out the reported results and says if the readings are too far apart to accept.
| Load | Result |
|---|---|
| S-1012A | Slump flow 700 mm, T500 2.2 s, J-ring 8 mm with no blocking, not segregated |
| S-1013A | Slump 55 mm, a true slump; compare with the 50 mm order using the adopted tolerance |

Air Content and Fresh Density
For air content, the meter readings are entered and the LIMS reports the result, flagging readings that do not agree well. For fresh density, the measure is picked from the register, so its calibrated capacity is used, and the empty and full weighings are entered.
| Test | Readings | Result |
|---|---|---|
| Apparent air content (S-1012A) | Retain every meter reading and the method’s repeat/agreement checks | Illustrative apparent result: 4.8%; corrected air content is not established here |
| Mass per unit volume (S-1012A) | Measure 6.95 L; 8.25 kg empty, 24.01 kg full | 2270 kg/m³ |
A 4.8% apparent result cannot be treated as corrected air content unless the applicable aggregate correction has been determined and applied as required. The density arithmetic is (24.01 − 8.25) / 0.00695 ≈ 2,268 kg/m³, shown here as 2,270 kg/m³; use the adopted method’s actual reporting precision.
Specimens Made from the Load
Each specimen gets a label printed on site, so it keeps its identity through transport, curing and testing. The LIMS records when each was moulded and how it was compacted, and for shrinkage prisms, the mould and the type of gauge studs.
| Load | Specimens |
|---|---|
| S-1012A | Cylinders C01 (7 days), C02 and C03 (28 days) |
| S-1013A | Beams B01 and B02 (150 mm), broken at 28 days |
| S-1013A | Shrinkage prisms P01 to P03, moulds M1 to M3 |

Bleeding
A bleeding test runs for an hour or more, so it is started on the load and finished on its own worksheet. The water rising from the specimen is drawn off at intervals and recorded until bleeding stops; the LIMS keeps the running total and works out the result.
| Time (min) | Drawn off (mL) | Running total (mL) |
|---|---|---|
| 15 | 8 | 8 |
| 30 | 12 | 20 |
| 45 | 10 | 30 |
| 60 | 8 | 38 |
| 90 | 9 | 47 |
| 120 | 4 | 51 |
For S-1013A, the example reports 0.00104 mL of bleed water per mm² of exposed specimen surface and 2% of the mixing water represented by the test specimen. To reproduce those calculations the record needs the specimen area, specimen quantity and relevant batch-water data, as specified by the method. Do not divide the water collected from one specimen by the water in the entire delivery.
Part 4: Pick Up and Cure the Specimens
Bad handling or curing can alter a specimen’s result and weaken its relevance to the concrete being assessed. Retain the result with the departure recorded; do not assume that every low result is a handling problem. The standards set when specimens are demoulded, how they are cured and how quickly each step must follow the last. Recording each step is how a laboratory shows a specimen was treated properly.
The technician who collects the specimens records the pickup and their condition. Each specimen is scanned or ticked, so the record shows when it left site and in what state.

| Specimen | Moulded | Picked up | Demoulded | Into curing |
|---|---|---|---|---|
| S-1012A cylinders | Day 0, 1:35 pm | Day 1, 9:10 am | Day 1, 10:00 am | Day 1, 10:05 am |
| S-1013A beams | Day 0, 2:55 pm | Day 1, 9:10 am | Day 2, in curing | Day 1, 10:10 am, in their moulds |
| S-1013A prisms | Day 0, 2:55 pm | Day 1, 9:10 am | Day 1, 2:40 pm | Day 1, 2:50 pm |
These collection and curing times are illustrative, not a compliant timetable for every method or climate. Record the initial curing protection and temperatures, condition at collection and transport arrangements as well as timestamps. A LIMS can flag departures only if the correct method rules are configured. It also stops records that cannot be true: a prism put into curing before it was demoulded, or a beam tested while still recorded as on site.
Part 5: Break the Cylinders and Beams
Strength tests are where small recording errors become large reporting errors: a cylinder broken against the wrong load, a 28-day cylinder broken early without anyone noticing, or a beam reported as if it broke normally when it did not.
Compressive Strength
The cylinders due today are collected into a breaking session. The machine and measuring checks are recorded once for the session, then each cylinder's dimensions, mass and maximum force are entered. The LIMS calculates the strength and the density, and records the fracture type.

| Cylinder | Age | Max force (kN) | Strength | Density |
|---|---|---|---|---|
| S-1012A-C01 | 7 days | 198.6 | 25.5 MPa | 2370 kg/m³ |
| S-1012A-C02 | 28 days | 352.4 | 45.0 MPa | 2370 kg/m³ |
| S-1012A-C03 | 28 days | 345.9 | 44.0 MPa | 2370 kg/m³ |
The 7-day result is an early indication, not a pass or fail on its own. The two 28-day cylinders agree closely, and together they give the sample's strength for assessment in Part 8.
Flexural Strength
The beams are tested on the flexure frame, using the span stored on its record. The technician enters the maximum force, the beam's measured section at the break, and where the beam broke.
| Beam | Age | Max force (kN) | Where it broke | Result |
|---|---|---|---|---|
| S-1013A-B01 | 28 days | 36.0 | Within the zone the method accepts | 4.8 MPa |
| S-1013A-B02 | 28 days | 34.5 | Within the zone the method accepts | 4.5 MPa |
A beam that breaks outside the zone the method accepts does not give a flexural strength, and the LIMS records it that way rather than letting it into an average. The displayed beam values are both at or above the example’s 4.5 MPa comparison value. Their validity and any lot decision still require measured sections, fracture locations, method-specific calculations and the project’s assessment rules.
Test Age Is Recorded, Not Assumed
Each specimen’s due time comes from the recorded age-reference timestamp required by its method and the planned test age, so the laboratory sees what is due each day. A specimen tested a day early or late is recorded with its actual age, so the report states what happened, not what was planned.
Part 6: Read the Shrinkage Prisms
Drying shrinkage is the shortening that occurs as hardened concrete loses moisture. The laboratory makes and cures prism specimens under AS 1012.8.4 and measures length change during controlled drying under AS 1012.13. Shrinkage can contribute to cracking when concrete is restrained, but this test does not predict crack width or location on its own. The example follows a set over eight weeks of drying. The result is a very small change in length, which makes careful records essential.
The LIMS keeps each prism's starting reading, the readings at each drying period, when each was taken and the drying room's conditions at the time. It works out each prism's shrinkage and the set's result, and marks any prism the method's rules leave out of the set result.
| Days of drying | Set result |
|---|---|
| 7 | 200 microstrain |
| 14 | 320 microstrain |
| 21 | 420 microstrain |
| 28 | 480 microstrain (illustrative set result; retain every prism reading) |
| 56 | 660 microstrain |
“Days of drying” starts at the nominated drying stage, not at casting. For scale, 660 microstrain over a hypothetical 250 mm gauge length corresponds to 0.165 mm of shortening. This helps explain why comparator checks and environmental records matter. Never exclude a prism merely because it is different: apply the method’s actual rules and document the technical basis.
Clients usually want a figure before eight weeks have passed, so the set is reported twice: an interim result at 28 days of drying and a final result at 56 days that supersedes it. The final carries the earlier readings on their original dates and adds the last.
The record protects against the common problems: a reading taken on the wrong day, a starting reading that never settled, a drying room out of its range, and a damaged prism quietly left in the set.
Part 7: Review and Approve
A completed test must pass the review and authorisation steps required by the laboratory’s quality system before report issue. This example separates the tester, technical reviewer and signatory; it is not a claim that every laboratory must use three different people. Record the actual permissions and approvals, and control impartiality and competence.
The reviewer checks that the measurements are plausible, that the calculation and rounding follow the method, that the specimen's history is complete, that the equipment was in date, and that anything flagged has a reason. The LIMS shows each result with its unrounded value, its measurements, the equipment and who did the test, so the reviewer checks the record itself rather than a summary.

If something is wrong, the reviewer returns the result with a reason. The tester corrects it, and the correction is kept beside the original value with its reason; nothing is overwritten. The signatory then approves results they did not perform.

Fresh concrete results are often needed the same day, while strengths arrive weeks later, so review happens in stages: each load's fresh results are approved on the day, and the strengths are reviewed as they are tested.
Part 8: Report and Assess
The report is what the client, the engineer and the auditor see. Each method sets what its report must state, and the concrete specification sets how strength is assessed against the grade.
The Fresh Concrete Field Report
The field report lists each load sampled on the visit, one row each, and can be issued before the technician leaves site once the fresh results are approved.
| Load | Docket | Workability | Air | Density | Bleeding | Specimens |
|---|---|---|---|---|---|---|
| S-1012A | CD-88437 | Slump flow 700 mm; record J-ring and stability observations | 4.8 % apparent | 2270 kg/m³ | 3 cylinders | |
| S-1013A | CD-88512 | True slump 55 mm; tolerance check recorded separately | 2 % | 2 beams, 3 prisms |

Strength and Assessment
The compressive strength report gives each cylinder's age, measurements, density and strength, with the load's details in the remarks. The displayed 28-day results, 45.0 and 44.0 MPa, have an arithmetic mean of 44.5 MPa. Use the adopted grouping, exclusion and calculation rules before treating it as a sample strength. A mean above the 40 MPa grade does not on its own establish AS 1379 conformity; apply the full project assessment, including other required samples and criteria. Retain unrounded calculations and measured dimensions. Early-age results can address separately specified requirements but do not replace the nominated later-age assessment.
The flexural report gives each beam's result, or notes a beam that broke where no result can be given. The drying shrinkage reports give each prism and the set result at each period, mark any prism left out of the set result, and the final report supersedes the interim.
Issuing
An issued report is fixed: its PDF and the data behind it do not change. If a correction is needed, the report is amended and re-issued, and the new issue says what it supersedes and why.

Reading the Results Together
| Question | Answer from this job |
|---|---|
| What fresh SCC evidence is recorded? | 700 mm spread, T500 2.2 s, J-ring 8 mm and no observed segregation; compare all with the specified limits |
| What does the walls strength result establish? | The illustrated pair averages 44.5 MPa; supply conformity needs the adopted assessment rules and the required result set |
| What does the pavement strength comparison show? | Both displayed beam values reach the example comparison value; method validity and lot assessment remain separate checks |
| How much did it shrink? | 480 microstrain at 28 days and 660 at 56 days, for comparison with the project's limit |
Each result can be traced back through the reports to the specimen, the load, the docket and the technician who sampled it. That traceability is what a LIMS is for.
Sources and Method Scope
This guide describes how concrete test records are kept and reported; it does not set out the test procedures. The tests are carried out to the AS 1012 methods and assessed under AS 1379 and the project's specification, and road authority specifications may add requirements. The example job, its numbers and its people are illustrative.
Related Resources
- Concrete Air Content Testing (AS 1012.4.2)
- Concrete Compressive Strength Testing (AS 1012.9)
- Concrete Flexural Strength Testing (AS 1012.11)
- Concrete Slump Testing (AS 1012.3.1)
- Concrete Testing in Australia: The Complete Guide
- Book a concrete pour (GeotechOS Lab help)
- Break concrete cylinders (GeotechOS Lab help)
- Concrete compliance (GeotechOS Lab help)
- Concrete sampling on site (GeotechOS Lab help)
- Equipment checks (GeotechOS Lab help)
- Make a laboratory test report (GeotechOS Lab help)
- Pick up specimens from site (GeotechOS Lab help)
- Review and approve results (GeotechOS Lab help)
- Set up your laboratory (GeotechOS Lab help)